Concrete Calculator

It works out the volume of concrete a slab, footing or pad needs, in cubic feet, yards and meters, and converts that into a count of pre-mixed bags.

IntermediateUpdated 2026-07-28Free · no sign-up

Concrete needed

1.36 yd³

36.7 cubic feet · 1.04 m³ · includes 10% waste

Cubic yards

1.36

Cubic feet

36.7

Cubic meters

1.04

40 lb bags

123

50 lb bags

98

60 lb bags

82

80 lb bags

62

At over a cubic yard, ready-mix delivery is normally cheaper and far less work than mixing 62 bags by hand.

What it calculates

It works out the volume of concrete a slab, footing or pad needs, in cubic feet, yards and meters, and converts that into a count of pre-mixed bags.

Why it matters

Concrete is ordered by the cubic yard and cannot be topped up once a pour begins. Under-ordering ruins a slab; over-ordering wastes money.

Who it's for

DIY builders pouring a patio or shed base, contractors ordering ready-mix, and anyone estimating a footing.

Formula

volume = length × width × (thickness ÷ 12)  |  cubic yards = cubic feet ÷ 27
V
Volume = length × width × thickness
yd³
Cubic yards — 27 cubic feet
w
Waste allowance for spillage and uneven subgrade

Worked example

A 10 ft × 10 ft slab, 4 inches thick

  1. 1Convert thickness: 4 in ÷ 12 = 0.333 ft
  2. 2Volume = 10 × 10 × 0.333 = 33.33 cu ft
  3. 3Cubic yards = 33.33 ÷ 27

1.23 cubic yards, or 56 bags of 80 lb mix

How the concrete calculator works

Volume is length times width times thickness, with the thickness converted from inches to feet first — that division by twelve is where most errors happen. Dividing cubic feet by 27 gives cubic yards, the unit ready-mix is sold in. Bag counts come from the yield printed on the bag: an 80 lb bag makes about 0.6 cubic feet, a 60 lb bag about 0.45.

Volume is length times width times thickness, with thickness converted from inches to feet first. That division by twelve is where most estimating errors happen — forget it and you will over-order by a factor of twelve.

Bag counts come from the yield printed on the bag: an 80 lb bag makes about 0.6 cubic feet and a 60 lb bag about 0.45. Above roughly one cubic yard, ready-mix delivery usually beats bags on both cost and effort.

Common mistakes

  • Forgetting to convert thickness from inches to feet, which overstates volume twelvefold.
  • Ordering no waste allowance — subgrade is never perfectly level, and 5–10% extra is standard.
  • Ignoring that a bagged pour of more than about a cubic yard is far cheaper as ready-mix.

Tips and best practice

  • Above roughly one cubic yard, ready-mix delivery usually beats bags on both cost and effort.
  • Add 10% on an uneven or unformed subgrade; the extra concrete finds every low spot.

Frequently asked questions

How much concrete do I need for a 10x10 slab?

At 4 inches thick, 33.3 cubic feet or 1.23 cubic yards — about 56 bags of 80 lb mix, before any waste allowance.

How many cubic feet are in a cubic yard?

Twenty-seven, because a cubic yard is 3 ft × 3 ft × 3 ft. That factor of 27 is why a slab measured in feet has to be divided down before ordering ready-mix.

How many bags of concrete are in a cubic yard?

About 45 bags of 80 lb mix, 60 of 60 lb, or 90 of 40 lb, based on their standard yields.

How much waste should I allow?

5% on a level, well-formed subgrade and up to 10% on rough ground. Running short mid-pour creates a cold joint, which is far worse than a little waste.

What thickness does a slab need?

4 inches suits patios and shed bases; driveways and anything carrying vehicles usually need 5–6 inches. Check local building codes.

Related calculators

Methodology & trust

Formula source
Standard volume calculation with published bag yields.